|
Temporary
Shoring, Retaining Walls and Demolition
An important niche
discipline at SDA is the design of temporary shoring for major construction
projects. We have supported major highways, railway lines and rivers for the
construction of bridge and building foundations. Often the shoring pit is dug
very close to major underground services that have to be fully protected against
any movement during the construction process.
Some typical recent
shoring projects are shown here:
Pearson
International Airport Expansion
SDA designed numerous
pits for the construction of bridge piers for the new
roadway system. Most were straightforward, but one or two posed major
technical challenges, like
the one shown here that had to be dug right next to gas lines, water mains, an
existing bridge and most important of all, a huge concrete tunnel carrying the
power and communications to Terminal 2. The tunnel was located at the top left
of the picture and the piles were drilled almost touching its sides. The picture
also conveys just how deep the hole was.
This
huge retaining wall had to carry
the load of a massive scaffolding system, right along the top, supporting the
formwork for the construction of one of the
big flyovers. This imposed a surcharge load of 6,000 psf for the entire length
of the retaining wall - equivalent to an additional 45ft of wall height!

Once the new roads and
bridges were built, the old ones had to be demolished. Naturally Canada's
busiest airport could not be shut down while this was going on, so special
procedures had to be adopted for the demolition process. The bridge illustrated
here had to be taken down in stages, however it was a post-tensioned design and
as soon as the reinforcing tendons were cut it was probable that the entire
bridge would collapse under its own weight onto the active roadway below. SDA
were hired to support the bridge using massive steel beams so that the
demolition could proceed safely.
|